I walked up to the top site this morning in driving snow. Significant progress has been made:-
a) A road bed has been dug out along the side of the existing path, almost as far along to where the path starts to slope steeply down towards the waterfalls.
b) The excavation for the pipes seems to have begun.
c) I think we saw the point at which the inlet is to take in water at the top (in main picture).