Pipe Connected

The pipe is now connected at the back of the pump house, and has been buried under the path to the Scottish Water installation and also down the hillside as far as I can see from the bottom. They have also just laid the first courses of breeze blocks which will form the pump house walls.




I have also heard that a complaint has been made to the planning authority regarding the placement of the pipe and associated construction work not being in line with the planning permission granted, and that SEPA are coming on site next week to examine the silt levels in the Donich (which is a protected water course under EU law because it provides water for the village.